Solving the Periodic Maintenance Scheduling Problem via Genetic Algorithm to Balance Workforce Levels and Maintenance Cost

Mohamed Ali Abdel-Fattah Mansour1

American Journal of Engineering and Applied Sciences, Volume 4, Issue 2, pp. 223–234 · doi.org/10.3844/ajeassp.2011.223.234

8,317 accesses5,798 downloads13 citations (Crossref)Metrics
Cite Check for updates

Abstract

Problem statement: In this article we address the multi-objective Periodic Maintenance Scheduling Problem (PMSP) of scheduling a set of cyclic maintenance operations for a given set of machines through a specified planning period to minimize the total variance of workforce levels measured in man-hours and maintenance costs with equal weights. Approach: The article proposed a mixed integer non-linear math programming model and a linearised model for the PMSP. Also, we proposed a Genetic Algorithm (GA) for solving the problem using a new genome representation considered as a new addition to the maintenance scheduling literature. The algorithms were compared on a set of representative test problems. Results: The developed GA proves its capability and superiority to find good solutions for the PMSP and outperforms solutions found by the commercial optimization package CPLEX. The results indicated that the developed algorithms were able to identify optimal solutions for small size problems up to 5 machines and 6 planning periods.The GAs defined solutions in 22 seconds consuming less than two kilobytes with a reliability of 0.84 while the nonlinear and linear models consumes on average 705 and 37 kilobytes respectively. Conclusion: The developed GA could define solutions of average performance of 0.34 and 0.8 for the linearized algorithm compared with lower bound defined by the nonlinear math programming model. We hope to expand the developed algorithms for integrating maintenance planning and aggregate production planning problems.

Licence and reuse

Free to read. This article carries the publisher’s copyright, as printed on it: © 2011 Science Publications. It is free to read; ask us before reusing it.

How to reuse this article

Responses (0)

Have a comment on this research? Sign in to respond. Responses are moderated and published with your name and affiliation; the authors are invited to reply. How we use your dataWrite a response

About this article

Cite this article

Mansour, M. A. A. (2011). Solving the Periodic Maintenance Scheduling Problem via Genetic Algorithm to Balance Workforce Levels and Maintenance Cost. American Journal of Engineering and Applied Sciences, 4(2), 223–234. https://doi.org/10.3844/ajeassp.2011.223.234

Licence
© Science Publications
Issue
Volume 4, Issue 2
Policies
Editorial independenceUse of generative AIData availabilityAppeals and complaints
Version
Version of record
Solving the Periodic Maintenance Scheduling Problem via Genetic Algorithm to Balance Workforce Levels and Maintenance CostAmerican Journal of Engineering and Applied Sciences · Volume 4, Issue 2 · pp. 223–234 · © Science PublicationsDownload